The next chapter in the project

What changed?

Follow data-center and power projects from one dated development to the next—with the earlier decision underneath.

45 dated developments · 30 selected data-center and power projects · Latest record check: September 9, 2026. Each project retains its own review date.

45 dated developments · newest event first

  1. Latest in this project’s record

    Pine Island, Minnesota

    Google / Echo Zone Pine Island campus

    Separate transmission hearings announced

    The EQB notice lists a September 14, 6 p.m. hearing in Pine Island, a September 15, 6 p.m. online hearing and a September 25 comment deadline for the proposed North Rochester–Skyway line, docket 26-135. Consult the linked notice for current arrangements.

    Previously · April 14, 2026: Service agreement filed. The regulator records Xcel and Echo Zone’s filing in docket 26-170; its status page lists the continuing public-comment period.

  2. Latest in this project’s record

    Londonderry Township, Pennsylvania

    Crane Clean Energy Center restart

    Connection and licensing milestones reported

    The operator reports a FERC waiver to transfer capacity interconnection rights and an NRC fuel-license amendment; it still targets 2027 operation.

    Previously · September 20, 2024: Restart plan and power contract announced. Constellation announced a 20-year agreement with Microsoft supporting the proposed restart.

  3. Latest in this project’s record

    Prince William County, Virginia

    Digital Gateway

    Later order changes the effective zoning

    The county’s August 5 update says the original zoning was restored following the July 29 order; the comprehensive-plan amendment remains.

    Previously · March 31, 2026: Appeals court invalidates approvals. Defective public notice invalidated the rezonings; the order kept land disturbance and construction prohibited pending further appeal.

  4. Latest in this project’s record

    Monterey Park, California

    1977 Saturn Street

    Measure NDC goes to voters; prohibition adopted

    The city placed Measure NDC on the June 2 ballot and subsequently confirmed the voter-adopted citywide prohibition. The Saturn Street application had already been withdrawn.

    Previously · May 6, 2026: City adopts prohibition. Ordinance 2278 removes independent data-center uses; the city’s later ballot information confirms the voter-adopted ban.

  5. Earlier development

    Monterey Park, California

    1977 Saturn Street

    City adopts prohibition

    Ordinance 2278 removes independent data-center uses; the city’s later ballot information confirms the voter-adopted ban.

    Previously · March 31, 2026: Applicant withdraws. HMC StratCap’s letter cites the moratorium and planned prohibition as unsuitable conditions for development.

  6. Earlier development

    Prince William County, Virginia

    Digital Gateway

    Appeals court invalidates approvals

    Defective public notice invalidated the rezonings; the order kept land disturbance and construction prohibited pending further appeal.

    Previously · December 2023: County adopts rezonings. Three approvals allowed the proposed development to advance into a legal challenge.

  7. Latest in this project’s record

    Kemmerer, Wyoming

    Kemmerer Power Station Unit 1

    Construction-permit decision recorded

    The docket follows the March 4 authorization to issue. NRC states that a separate operating license is required.

    Previously · March 28, 2024: Construction application submitted. TerraPower submitted its construction-permit application.

  8. Latest in this project’s record

    San Marcos, Texas

    Francis Harris Lane proposal

    Plan change fails

    The February 17 meeting concluded in the early hours of February 18 with the prerequisite amendment denied.

    Previously · February 11, 2026: Organizing before the hearing. Save Our Springs promoted a town hall, petition and contacts with decision-makers.

  9. Latest in this project’s record

    Québec–Lewiston corridor, Maine

    New England Clean Energy Connect

    Commercial operation begins

    EIA records the start of commercial operation. Its later January analysis also documents interrupted imports during severe cold.

    Previously · April 20, 2023: Jury verdict supports proceeding. Avangrid reports that the Cumberland County jury found in its favor on vested rights.

  10. Earlier development

    Québec–Lewiston corridor, Maine

    New England Clean Energy Connect

    Jury verdict supports proceeding

    Avangrid reports that the Cumberland County jury found in its favor on vested rights.

    Previously · August 30, 2022: Court orders further factfinding. The court identifies a conditional vested-rights protection and remands for findings rather than itself resolving every factual issue.

  11. Earlier development

    Québec–Lewiston corridor, Maine

    New England Clean Energy Connect

    Court orders further factfinding

    The court identifies a conditional vested-rights protection and remands for findings rather than itself resolving every factual issue.

    Previously · November 2, 2021: Voters approve restrictions. The Maine court describes a referendum that effectively halted the project.

Event dates are not source-check dates. This is an edited record, not a live permit feed.

Have a later vote or a changed proposal? Send the source.