Project record

Digital Gateway

Prince William County, Virginia

Construction restricted by court

Rezoning approvals void; the county reports the original zoning restored.

The comprehensive-plan amendment remains in place. A fresh rezoning would require the ordinary application and public-hearing process.

Last documented milestone:
Sources checked:

Developer / project sponsor
Compass Datacenters and QTS
Participants named in the linked record
Nearby resident plaintiffs; Piedmont Environmental Council; county and developers.

The decision trail

  1. County adopts rezonings

    Three approvals allowed the proposed development to advance into a legal challenge.

  2. Appeals court invalidates approvals

    Defective public notice invalidated the rezonings; the order kept land disturbance and construction prohibited pending further appeal.

  3. Later order changes the effective zoning

    The county’s August 5 update says the original zoning was restored following the July 29 order; the comprehensive-plan amendment remains.

Open the supporting records

  1. 1. Court opinion · Court of Appeals of Virginia

    Virginia Court of Appeals: Digital Gateway rezoning and notice decision

    A dated appeals-court decision, not a statement that all litigation has ended. Page 53 allows further appeal while keeping land disturbance and construction prohibited under the order.

    Publication: 2026-03-31 · Checked: 2026-09-07
    Location in source: PDF pages 1–4: parties; pages 26–34: notice; pages 51–53: disposition and partial stay

    Source record: digital-gateway-appeal
  2. 2. Participant account · Piedmont Environmental Council / Julie Bolthouse

    PEC describes its opposition and court filing in Digital Gateway

    PEC opposed the project. Used for its stated participation and concerns; the court opinion, not the advocacy account, establishes the legal result.

    Publication: 2026-04-07 · Checked: 2026-09-07
    Location in source: Opening timeline; Why PEC Fought This Project

    Source record: pec-digital-gateway-response
  3. 3. Local government status page · Prince William County Planning Office

    PW Digital Gateway: status following the July 29 order

    County implementation account; does not establish that every future appeal or application has ended.

    Publication: 2026-08-05 · Checked: 2026-09-09
    Location in source: Update: August 5, 2026; current zoning and Next Steps.

    Source record: digital-gateway-county-july-order

A later vote, revised application or court order can change this record. Send a sourced update.