Power & Possibilities
Power needs a path to the grid. A permit is not an operating plant. A battery is not a fuel supply. Follow what each project can deliver—and what happened on its way there.
Produce Generation creates electricity. The plant’s rating is not its annual output.
Store MW measures discharge power; MWh measures how much energy a battery can hold.
Deliver Transmission moves electricity. A line’s capacity is not new generation.
Download shown records (JSON)
Hurdles can be historical or unresolved; matching a filter does not mean a project is currently blocked. Checked September 7, 2026.
All records remain visible below. Filters require JavaScript.
Generation · Michigan
Holtec International
Restart preparations Holtec reported the start of fuel loading on August 30, 2026, a step toward—not proof of—commercial generation.
Operator-stated design electrical output 805 MW Generation · Pennsylvania
Constellation
Restart preparations Constellation reported interconnection-rights and fuel-license progress in August 2026, with restart still targeted for 2027.
Approximately; planned restored electrical capacity 835 MW Transmission · New Mexico / Arizona
Pattern Energy; Hitachi Energy
In service — documented Hitachi Energy and Pattern Energy reported the transmission link fully operational in June 2026.
Transmission capability 3,000 MW No specific blocking cause established in the linked record.
Transmission · New York
Transmission Developers / Hydro-Québec
In service — documented The developer reported commercial operation by June 16, 2026, while describing temporary restrictions on contracted energy sales.
Transmission capability 1,250 MW Generation · Wyoming
US SFR Owner / TerraPower
Construction permit issued NRC’s docket records the construction-permit decision on March 9, 2026. Operating approval is a separate step.
Proposed electrical generation 345 MW
Temporary electrical output with storage 500 MW Transmission · Maine
NECEC Transmission / Avangrid; Hydro-Québec
In service — documented The 1,200 MW line entered commercial operation on January 16, 2026, after a referendum and litigation interrupted its development.
Transmission transfer capability 1,200 MW Generation · Utah
Intermountain Power Agency; LADWP operating agent
In service — documented LADWP reported using the new natural-gas units in December 2025. Hydrogen blending remained a future step in the cited announcement.
Replacement-unit electrical capacity 840 MW No specific blocking cause established in the linked record.
Transmission · Kansas / Missouri / Illinois
Invenergy
Financing decision recorded DOE terminated its conditional Phase 1 financing commitment in July 2025. The developer continues to describe a privately led transmission proposal.
Planned full-project transmission capability 5,000 MW Generation + storage · Nevada
Primergy / Quinbrook
In service — documented The developer announced full commercial operation in July 2024, after reporting supply-chain and inflation challenges.
Solar generation rating 690 MW
Battery discharge-power rating 380 MW
Operator-reported battery energy 1,400 MWh Storage · Arizona
Plus Power; Salt River Project
In service — documented SRP identifies Sierra Estrella as a 250 MW, four-hour battery that entered service in 2024.
Battery discharge-power rating 250 MW
Derived rated energy: 250 MW × 4 hours 1,000 MWh No specific blocking cause established in the linked record.
No matching power projects. Clear a filter to see more of this selected collection.
Scope and ratings This is not a national inventory, an opposition rate or a list of dedicated AI power supplies. Capacities describe different equipment and are not added into one total. Historical hurdles are not automatically current delays.
For the broader generation-connection queue, see Berkeley Lab’s findings . Its dataset does not include data-center load connections.