Power needs a path to the grid.

A permit is not an operating plant. A battery is not a fuel supply. Follow what each project can deliver—and what happened on its way there.

Produce

Generation creates electricity. The plant’s rating is not its annual output.

Store

MW measures discharge power; MWh measures how much energy a battery can hold.

Deliver

Transmission moves electricity. A line’s capacity is not new generation.

Hurdles can be historical or unresolved; matching a filter does not mean a project is currently blocked. Checked September 7, 2026.

  • Generation · Michigan

    Palisades restart

    Holtec International

    Restart preparations

    Holtec reported the start of fuel loading on August 30, 2026, a step toward—not proof of—commercial generation.

    Operator-stated design electrical output
    805 MW
    • Equipment / commissioningFurther steps required

      Refurbishment and fuel loading are documented restart steps; commissioning is not yet commercial service in this source.

    Timeline, capacity & sources ↗
  • Generation · Pennsylvania

    Crane Clean Energy Center restart

    Constellation

    Restart preparations

    Constellation reported interconnection-rights and fuel-license progress in August 2026, with restart still targeted for 2027.

    Approximately; planned restored electrical capacity
    835 MW
    • Grid connection / market accessHistorical hurdle

      The operator reports that a waiver addressed a capacity-interconnection-rights requirement.

    • Permitting / licensingFurther steps required

      Restart remains a future milestone despite the reported licensing progress.

    Timeline, capacity & sources ↗
  • Transmission · New Mexico / Arizona

    SunZia Transmission

    Pattern Energy; Hitachi Energy

    In service — documented

    Hitachi Energy and Pattern Energy reported the transmission link fully operational in June 2026.

    Transmission capability
    3,000 MW

    No specific blocking cause established in the linked record.

    Timeline, capacity & sources ↗
  • Transmission · New York

    Champlain Hudson Power Express

    Transmission Developers / Hydro-Québec

    In service — documented

    The developer reported commercial operation by June 16, 2026, while describing temporary restrictions on contracted energy sales.

    Transmission capability
    1,250 MW
    • Grid connection / market accessDated issue; later resolution unconfirmed

      Temporary market restrictions were reported at launch; the linked record does not document their later resolution.

    Timeline, capacity & sources ↗
  • Generation · Wyoming

    Kemmerer Power Station Unit 1

    US SFR Owner / TerraPower

    Construction permit issued

    NRC’s docket records the construction-permit decision on March 9, 2026. Operating approval is a separate step.

    Proposed electrical generation
    345 MW
    Temporary electrical output with storage
    500 MW
    • Permitting / licensingFurther steps required

      Construction approval is documented; the plant still needs a separate operating license before it can operate.

    Timeline, capacity & sources ↗
  • Transmission · Maine

    New England Clean Energy Connect

    NECEC Transmission / Avangrid; Hydro-Québec

    In service — documented

    The 1,200 MW line entered commercial operation on January 16, 2026, after a referendum and litigation interrupted its development.

    Transmission transfer capability
    1,200 MW
    Timeline, capacity & sources ↗
  • Generation · Utah

    Intermountain Power Project Renewed

    Intermountain Power Agency; LADWP operating agent

    In service — documented

    LADWP reported using the new natural-gas units in December 2025. Hydrogen blending remained a future step in the cited announcement.

    Replacement-unit electrical capacity
    840 MW

    No specific blocking cause established in the linked record.

    Timeline, capacity & sources ↗
  • Transmission · Kansas / Missouri / Illinois

    Grain Belt Express

    Invenergy

    Financing decision recorded

    DOE terminated its conditional Phase 1 financing commitment in July 2025. The developer continues to describe a privately led transmission proposal.

    Planned full-project transmission capability
    5,000 MW
    • FinancingDated issue; later resolution unconfirmed

      A conditional guarantee was withdrawn; subsequent financial close is not confirmed by these sources.

    Timeline, capacity & sources ↗
  • Generation + storage · Nevada

    Gemini Solar + Storage

    Primergy / Quinbrook

    In service — documented

    The developer announced full commercial operation in July 2024, after reporting supply-chain and inflation challenges.

    Solar generation rating
    690 MW
    Battery discharge-power rating
    380 MW
    Operator-reported battery energy
    1,400 MWh
    • Equipment / commissioningHistorical hurdle

      The developer says it navigated supply-chain and inflation challenges before service; it does not identify them as current blockers.

    Timeline, capacity & sources ↗
  • Storage · Arizona

    Sierra Estrella Energy Storage

    Plus Power; Salt River Project

    In service — documented

    SRP identifies Sierra Estrella as a 250 MW, four-hour battery that entered service in 2024.

    Battery discharge-power rating
    250 MW
    Derived rated energy: 250 MW × 4 hours
    1,000 MWh

    No specific blocking cause established in the linked record.

Scope and ratings

This is not a national inventory, an opposition rate or a list of dedicated AI power supplies. Capacities describe different equipment and are not added into one total. Historical hurdles are not automatically current delays.

For the broader generation-connection queue, see Berkeley Lab’s findings. Its dataset does not include data-center load connections.