Power project
Gemini Solar + Storage
Clark County, Nevada · Generation + storage
In service — documented
The developer announced full commercial operation in July 2024, after reporting supply-chain and inflation challenges.
The battery shifts energy in time. Its power and energy ratings are not additional continuous solar generation.
Last documented milestone:
Sources checked: September 7, 2026
- Developer / operator
- Primergy / Quinbrook
- Technology
- Solar generation and battery storage
What the equipment is rated to do
Capacity is not annual energy output or guaranteed availability. MW and MWh describe different quantities.
The documented hurdles
- Equipment / commissioningHistorical hurdle
The developer says it navigated supply-chain and inflation challenges before service; it does not identify them as current blockers.
The dated trail
Commercial operation announced
Primergy and Quinbrook reported the solar and co-located battery system fully operational.
Open the supporting records
1. Operator announcement · Primergy / Quinbrook
Gemini solar and storage reaches commercial operation
Solar power, battery discharge power and stored energy are distinct quantities. Supplier and inflation challenges are the developer’s account.
Publication: 2024-07-18 · Checked: 2026-09-07
Source record: gemini-operation
Location in source: Opening announcement; 690 MW solar and 380 MW / 1,400 MWh storage paragraphs