Power project

Palisades restart

Covert Township, Michigan · Generation

Restart preparations

Holtec reported the start of fuel loading on August 30, 2026, a step toward—not proof of—commercial generation.

The operator describes inspections, refurbishment, testing and equipment upgrades. Fuel loading must not be counted as electricity already supplied to the grid.

Last documented milestone:
Sources checked: September 7, 2026

Developer / operator
Holtec International
Technology
Nuclear restart

What the equipment is rated to do

Operator-stated design electrical output
805 MW
Original rating ↗

Capacity is not annual energy output or guaranteed availability. MW and MWh describe different quantities.

The documented hurdles

  • Equipment / commissioningFurther steps required

    Refurbishment and fuel loading are documented restart steps; commissioning is not yet commercial service in this source.

The dated trail

  1. Fuel-loading process begins

    Holtec describes entry into the fuel-loading sequence and further steps toward restart.

Open the supporting records

  1. 1. Operator announcement · Holtec International

    Palisades begins fuel loading ahead of restart

    Fuel loading is a restart milestone, not proof of commercial generation. The owner’s 805 MWe rating is retained as stated.

    Publication: 2026-08-30 · Checked: 2026-09-07
    Location in source: Opening paragraphs: fuel loading, Mode 6, refurbishment and 805 MWe design output

    Source record: palisades-fuel-loading