Project record

1977 Saturn Street

Monterey Park, California

Application withdrawn

Application withdrawn; citywide prohibition followed.

The named application ended. The city’s later ban also affects future independent data-center proposals.

Last documented milestone:
Sources checked:

Developer / project sponsor
HMC StratCap
Participants named in the linked record
City of Monterey Park; Yes on Measure NDC campaign committee.

The decision trail

  1. Applicant withdraws

    HMC StratCap’s letter cites the moratorium and planned prohibition as unsuitable conditions for development.

  2. City adopts prohibition

    Ordinance 2278 removes independent data-center uses; the city’s later ballot information confirms the voter-adopted ban.

  3. Measure NDC goes to voters; prohibition adopted

    The city placed Measure NDC on the June 2 ballot and subsequently confirmed the voter-adopted citywide prohibition. The Saturn Street application had already been withdrawn.

Open the supporting records

  1. 1. Applicant correspondence · HMC StratCap / DigiCo, filed with Monterey Park

    1977 Saturn Street: applicant's withdrawal letter

    The applicant states its own reason for withdrawal. This establishes the application outcome, not every motive behind the city's restrictions.

    Publication: 2026-03-31 · Checked: 2026-09-07
    Location in source: Single-page letter, paragraphs 2–4

    Source record: monterey-withdrawal
  2. 2. Adopted ordinance · City of Monterey Park

    Monterey Park Ordinance 2278: data-center prohibition

    The text distinguishes prohibited data-center uses from permitted subordinate accessory server rooms. It is an enacted zoning record, not the later ballot tally.

    Publication: 2026-05-06 · Checked: 2026-09-07
    Location in source: Sections 5–11; adoption and vote on PDF pages 9–10

    Source record: monterey-ordinance-2278
  3. 3. Current municipal explanation · City of Monterey Park

    City confirmation of the voter-adopted data-center ban

    Used only to confirm the existing ban, not to support or oppose the separate November housing measure. The page is not a certified election-results table.

    Publication: 2026 housing-ballot information · Checked: 2026-09-07
    Location in source: Key Facts: Data Center Ban Affirmed; FAQ 3

    Source record: monterey-ban-confirmation
  4. 4. Campaign disclosure register · Monterey Park City Clerk

    Yes on Measure NDC: campaign filing register

    Establishes a disclosed ballot-measure committee and available filings. No aggregate spending or donor-direction claim is inferred from the register.

    Publication: March–June 2026 filings · Checked: 2026-09-07
    Location in source: Statement of organization, contribution reports and Form 460 entries

    Source record: monterey-ndc-filings
  5. 5. Official ballot information · City of Monterey Park

    Monterey Park: June 2, 2026 special municipal election

    Establishes the ballot date and subject. Read alongside the city’s later confirmation of the adopted prohibition; this page alone is not a certified vote tally.

    Publication: 2026-06-02 election · Checked: 2026-09-07
    Location in source: Election date and Measure NDC, Proposition to Prohibit Data Centers in Monterey Park.

    Source record: monterey-june-election

A later vote, revised application or court order can change this record. Send a sourced update.