Source document
Crane restart and Microsoft power-purchase agreement
Constellation
A power-purchase agreement is not a dedicated physical wire to a particular data center; restart remained conditional.
Open the original source ↗- Record type
- Operator announcement
- Publication date / scope
- 2024-09-20
- Last checked
- 2026-09-07
- Relevant location
- Restart scope, approximately 835 MW and 20-year Microsoft agreement
- Stable source ID
- crane-restart-plan
Where this source is used
Crane Clean Energy Center restart
Constellation reported interconnection-rights and fuel-license progress in August 2026, with restart still targeted for 2027. Last documented milestone: August 6, 2026.