Blocked in 2021. Carrying power in 2026.

Maine voters approved restrictions that halted the NECEC transmission project. A court case and jury verdict changed its path; EIA records commercial operation beginning January 16, 2026.

The short version

  • The Maine court describes the November 2021 referendum as effectively halting the project.
  • A later jury verdict favored the developer; the 1,200 MW line entered commercial operation in January 2026.

Why it matters. A successful vote against a project can be followed by a different legal and construction outcome. The dated trail shows what the opposition achieved—and what happened afterward.

Paper-cut illustration of a transmission corridor through a forest, with water, a distant town and planning sheets.
AI-generated conceptual illustration of a northern electricity corridor; not the actual NECEC route, a project photograph or a source document.

The ballot was not the last chapter

In November 2021, Maine voters approved restrictions on high-impact transmission construction. The state’s court opinion, paragraphs 2 and 20, describes the result: the initiative effectively halted New England Clean Energy Connect.

The dispute then turned on whether construction already undertaken gave the developer protected rights to continue. The August 2022 ruling sent that factual question back for further proceedings. In April 2023, Avangrid reported that a jury had found in its favor.

The eventual result appears in an operating record: EIA dates commercial service to January 16, 2026. Follow the complete project trail.

A line is capacity—not a promise of constant imports

The new connection can transfer 1,200 MW. But EIA also documented interrupted imports during January’s severe cold, when Québec limited exports to meet its own demand.

Both facts matter. The line reached service after a documented halt, and the amount it carries still depends on operating conditions. Neither the original vote nor the capacity rating tells the whole story.

A dated record

  1. November 2, 2021

    Voters approve the restrictions described in the court record.

    Maine Supreme Judicial Court · source ↓
  2. August 30, 2022

    Maine's highest court remands for further findings on vested rights.

    Maine Supreme Judicial Court · source ↓
  3. April 20, 2023

    Avangrid reports a jury verdict in its favor.

    Avangrid · source ↓
  4. January 16, 2026

    Commercial operation begins, according to EIA.

    U.S. Energy Information Administration · source ↓

The supporting record

Public recordClaim 1

The Maine Supreme Judicial Court records the November 2, 2021 vote and the resulting restrictions that effectively halted the project.

Reported findingClaim 2

The 2022 court decision required further factual findings on vested rights; Avangrid reported a favorable Cumberland County jury verdict on April 20, 2023.

Operational recordClaim 3

EIA records commercial operation of the 1,200 MW NECEC transmission line beginning January 16, 2026.

What we do not yet know

  • The separate contribution of each campaign or participant to the vote, project costs or elapsed development time.

Original documents, with context

Sources you can inspect

  1. 1. Court opinion · Maine Supreme Judicial Court

    NECEC Transmission: referendum and vested-rights decision

    The court remanded for factual findings on vested rights; this was not itself the later jury verdict or an operating authorization.

    Publication: 2022-08-30 · Checked: 2026-09-07
    Location in source: Paragraphs 2, 20 and 51–53; disposition on pages 38–39

    Source record: necec-2022-opinion
  2. 2. Developer statement · Avangrid

    Avangrid reports the NECEC jury verdict

    A party’s account of the verdict, not an independent assessment of project benefits.

    Publication: 2023-04-20 · Checked: 2026-09-07
    Location in source: Statements following the Cumberland County jury decision

    Source record: necec-2023-verdict
  3. 3. Operational analysis · U.S. Energy Information Administration

    NECEC enters service; winter trade flows change

    Transfer capacity is not guaranteed hourly delivery. The report describes a dated operating period, not current dispatch.

    Publication: 2026-01-30 · Checked: 2026-09-07
    Location in source: Opening paragraphs; January 16 start and January 24–27 power-flow discussion

    Source record: necec-eia-operation