Blocked in 2021. Carrying power in 2026.
Maine voters approved restrictions that halted the NECEC transmission project. A court case and jury verdict changed its path; EIA records commercial operation beginning January 16, 2026.
The short version
- The Maine court describes the November 2021 referendum as effectively halting the project.
- A later jury verdict favored the developer; the 1,200 MW line entered commercial operation in January 2026.
Why it matters. A successful vote against a project can be followed by a different legal and construction outcome. The dated trail shows what the opposition achieved—and what happened afterward.

The ballot was not the last chapter
In November 2021, Maine voters approved restrictions on high-impact transmission construction. The state’s court opinion, paragraphs 2 and 20, describes the result: the initiative effectively halted New England Clean Energy Connect.
The dispute then turned on whether construction already undertaken gave the developer protected rights to continue. The August 2022 ruling sent that factual question back for further proceedings. In April 2023, Avangrid reported that a jury had found in its favor.
The eventual result appears in an operating record: EIA dates commercial service to January 16, 2026. Follow the complete project trail.
A line is capacity—not a promise of constant imports
The new connection can transfer 1,200 MW. But EIA also documented interrupted imports during January’s severe cold, when Québec limited exports to meet its own demand.
Both facts matter. The line reached service after a documented halt, and the amount it carries still depends on operating conditions. Neither the original vote nor the capacity rating tells the whole story.
A dated record
- November 2, 2021
Voters approve the restrictions described in the court record.
Maine Supreme Judicial Court · source ↓ - August 30, 2022
Maine's highest court remands for further findings on vested rights.
Maine Supreme Judicial Court · source ↓ - April 20, 2023
Avangrid reports a jury verdict in its favor.
Avangrid · source ↓ - January 16, 2026
Commercial operation begins, according to EIA.
U.S. Energy Information Administration · source ↓
The supporting record
The Maine Supreme Judicial Court records the November 2, 2021 vote and the resulting restrictions that effectively halted the project.
The 2022 court decision required further factual findings on vested rights; Avangrid reported a favorable Cumberland County jury verdict on April 20, 2023.
EIA records commercial operation of the 1,200 MW NECEC transmission line beginning January 16, 2026.
What we do not yet know
- The separate contribution of each campaign or participant to the vote, project costs or elapsed development time.
Original documents, with context
Sources you can inspect
1. Court opinion · Maine Supreme Judicial Court
NECEC Transmission: referendum and vested-rights decision
The court remanded for factual findings on vested rights; this was not itself the later jury verdict or an operating authorization.
Publication: 2022-08-30 · Checked: 2026-09-07
Source record: necec-2022-opinion
Location in source: Paragraphs 2, 20 and 51–53; disposition on pages 38–392. Developer statement · Avangrid
Avangrid reports the NECEC jury verdict
A party’s account of the verdict, not an independent assessment of project benefits.
Publication: 2023-04-20 · Checked: 2026-09-07
Source record: necec-2023-verdict
Location in source: Statements following the Cumberland County jury decision3. Operational analysis · U.S. Energy Information Administration
NECEC enters service; winter trade flows change
Transfer capacity is not guaranteed hourly delivery. The report describes a dated operating period, not current dispatch.
Publication: 2026-01-30 · Checked: 2026-09-07
Source record: necec-eia-operation
Location in source: Opening paragraphs; January 16 start and January 24–27 power-flow discussion
Corrections & additional evidence · support@aipublicopinion.com