Queued Up: 2026 edition
Lawrence Berkeley National Laboratory / GridTracker
Generation and storage requests through 2025, not data-center load requests. Queue volume is proposed capacity, not a construction forecast. Data licensed CC BY 4.0.
Open the original source ↗- Record type
- Research report
- Publication date / scope
- 2026-05
- Last checked
- 2026-09-07
- Relevant location
- Abstract, scope and key highlights; linked project-level workbook
- Stable source ID
- lbl-queues-2026
Where this source is used
Thousands of power projects are waiting for a grid connection
- Berkeley Lab reports about 8,200 active generation and storage projects seeking transmission interconnection at the end of 2025. Research result
- In regions with data, projects built in 2025 had a median interval of more than five years between their interconnection request and commercial operation. Research result